Koh Phangan's 2025–2026 villa development pipeline: named projects, where they cluster, and what it signals
Koh Phangan counted 41 active residential projects and 438 units worth a combined ฿7.94 billion by Q1 2026, with holiday villas making up the large majority of new supply. This guide looks at the supply side specifically — where new construction is concentrated, a few named projects moving through it, and what the pattern means for a buyer weighing a resale plot against something new.
Vladimir Buryi · Founder, Right Way Phangan
Updated 31 July 2026
How much new villa and residential development is actually happening on Koh Phangan right now, and where? As of Q1 2026 the island had 41 active residential projects comprising 438 units worth roughly ฿7.94 billion, after adding more than 100 new units a year in both 2024 and 2025. Koh Phangan property market in 2026 covers the pricing and investment-outlook side of that data; this guide covers the supply side — which projects are actually being built, where they cluster, and what that tells a buyer.
The pipeline by segment
- Holiday villas dominate — 26 projects, 294 units, ฿6.83 billion combined value: the large majority of new supply on the island.
- Condominiums remain a small, tightly constrained segment — just 4 projects and 66 units, worth ฿380 million.
- Housing estates — 11 projects, 78 units, ฿730 million.
- Supply growth — around 231 new vacation homes were added across 2024–2025, with 131 of those launched in 2025 alone.
Where the new supply is concentrated
- Western and northwestern coastline — Mae Haad, Haad Yao and Hin Kong are the current centre of gravity for new villa construction. See Buying in Mae Haad, Haad Yao / Haad Salad and Hin Kong.
- Sri Thanu and Haad Yao — where most of the island's limited condominium supply is concentrated. See Buying in Sri Thanu.
- Thong Sala and Ban Tai — favoured by yield-focused buyers for liquidity and access. See Thong Sala and Ban Tai / Ban Khai.
- Chaloklum — also emerging as a boutique villa location, including some of the named projects below. See Buying in Chaloklum.
Named projects moving through the pipeline
A few examples currently marketed by island agencies illustrate the scale of what's actually being built — small, boutique developments rather than mass housing:
- 7 Palms (Chaloklum) — a 48-unit boutique development delivered in two phases: phase 1 (24 units) around September 2025, phase 2 (24 units) targeted for March 2026.
- Sunset Paradise (Sri Thanu) — 8 villas on a 1,600 m² plot, construction started May 2024 with completion targeted around August 2025.
- Terra Village — 1–3 bedroom pool villas (roughly 200–280 m² built-up on 315–718 m² plots), targeted for completion in Q4 2026.
- Samma Villas (near Hin Kong) — targeted for completion in Q1 2026.
These figures come from developer and agency marketing, not official filings — treat unit counts and completion dates as indicative, and verify current construction status, permits and the underlying land title directly before relying on any brochure timeline. See Buying off-plan on Koh Phangan for how to vet a developer properly.
What it signals for buyers
Larger, listed Thai developers — Supalai and Ornsirin Holding among them — entering the market in 2026 signals Koh Phangan moving from one-off, owner-built villas toward a more developer-driven pipeline. But the total footprint is still small: 438 units island-wide is a market of dozens of boutique projects, not mass-market supply, so a name entering the market is not yet a guarantee of scale or standardised quality.
Villas dominating over condos in the pipeline reflects land economics and the 2025 environmental zoning as much as demand — condominium projects need land and permitting that survive the island's building-zone rules, which constrains where and how large a condo project can be. And Colliers' own caution about the wider Samui/Phangan market applies just as much project-by-project here: success depends on land-title verification, location and realistic pricing, not the render on the marketing page. A new, polished project deserves the same diligence as a resale plot — see Due diligence before buying — plus confirmation of whether OCPB's off-plan deposit protections actually apply to that specific project.
Key points
- Q1 2026: 41 active residential projects on Koh Phangan (438 units, ~฿7.94bn); holiday villas are 26 of those projects (294 units, ฿6.83bn) — the dominant new-supply type, ahead of condos (4 projects) and housing estates (11 projects).
- New supply has run above 100 units a year in both 2024 and 2025 (231 combined, 131 in 2025 alone).
- New villa construction concentrates on the western/northwestern coast (Mae Haad, Haad Yao, Hin Kong) and increasingly Chaloklum; condo supply clusters in Sri Thanu/Haad Yao; Thong Sala/Ban Tai draw yield-focused buyers.
- Listed developers (Supalai, Ornsirin Holding) entering in 2026 signals the market professionalising, but total supply is still small — this is boutique-project growth, not mass development.
- Named off-plan projects and their completion dates come from agency marketing, not official filings — verify permits, land title and developer track record directly rather than relying on a brochure timeline.
Sources
General information, not legal advice. Thai property law is fact-specific — verify any structure with a licensed Thai lawyer before you commit. Independent legal due diligence is part of every transaction we handle.
From reading to doing.
Every property we list passes checks like these — title, zoning, access and the real numbers — before it goes live. Browse what’s available, or find out what your own land or villa is worth.